HR2072
On Union Calendar
To require the Federal Energy Regulatory Commission to extend the time period during which licensees are required to commence construction of certain hydropower projects.
- Federal
- House
- Introduced Mar 11, 2025
- Session 119
Bill Text
Version RHIn this section, the term covered project means a hydropower project with respect to which the Federal Energy Regulatory Commission issued a license before March 13, 2020.
Notwithstanding section 13 of the Federal Power Act (16 U.S.C. 806), on the request of a licensee of a covered project, the Federal Energy Regulatory Commission may, after reasonable notice and for good cause shown, extend in accordance with subsection (c) the period during which the licensee is required to commence construction of the covered project for not more than an additional 6 years beyond the 8 years authorized by that section.
An extension of time to commence construction of a covered project under subsection (b) shall—
consist of not more than 3 consecutive 2-year periods;
begin on the date on which the final extension of the period for commencement of construction granted to the licensee under section 13 of the Federal Power Act (16 U.S.C. 806) expires; and
end on the date that is not more than 6 years after the latest date to which the Federal Energy Regulatory Commission is authorized to extend the period for commencement of construction under that section.
If the time period required under section 13 of the Federal Power Act (16 U.S.C. 806) to commence construction of a covered project expires after December 31, 2023, and before the date of enactment of this Act—
the Federal Energy Regulatory Commission may reinstate the license for the applicable project effective as of the date of expiration of the license; and
the extension authorized under subsection (b) shall take effect on the date of that expiration.
Notwithstanding section 13 of the Federal Power Act (16 U.S.C. 806), on the request of a licensee of a covered project, the Federal Energy Regulatory Commission may, after reasonable notice and for good cause shown, extend in accordance with subsection (c) the period during which the licensee is required to commence construction of the covered project for not more than an additional 6 years beyond the 8 years authorized by that section.
An extension of time to commence construction of a covered project under subsection (b) shall—
consist of not more than 3 consecutive 2-year periods;
begin on the date on which the final extension of the period for commencement of construction granted to the licensee under section 13 of the Federal Power Act (16 U.S.C. 806) expires; and
end on the date that is not more than 6 years after the latest date to which the Federal Energy Regulatory Commission is authorized to extend the period for commencement of construction under that section.
If the time period required under section 13 of the Federal Power Act (16 U.S.C. 806) to commence construction of a covered project expires after December 31, 2023, and before the date of enactment of this Act—
the Federal Energy Regulatory Commission may reinstate the license for the applicable project effective as of the date of expiration of the license; and
the extension authorized under subsection (b) shall take effect on the date of that expiration.
Legislative Timeline
8 actions-
Reported by the Committee on Energy and Commerce. H. Rept. 119-477.
-
Reported by the Committee on Energy and Commerce. H. Rept. 119-477.
-
Placed on the Union Calendar, Calendar No. 408.
-
Committee Consideration and Mark-up Session Held
-
Ordered to be Reported by the Yeas and Nays: 44 - 0.
-
Introduced in House
-
Introduced in House
-
Referred to the House Committee on Energy and Commerce.